ROCHESTER — A
request to raise a portion of 49 acres
in southwest Rochester out of a 100-year floodplain along Cascade Creek is moving forward.
“They are not building anything that’s being proposed; it’s just the fill and excavation (of the site),” Community Development planner Elliot Mohler said of the conditional-use permit being sought.
The Rochester Planning and Zoning Commission supported recommendation for approval on Wednesday, making way for a Rochester City Council decision related to the site southeast of the Country Club Road intersection with 45th Avenue Southwest as early as next month.
Bill Tointon, land development director for WSE Massey Engineering and Surveying Ltd., said the request is the first step toward future development, pointing out the developer, Texas-based ML Group I, LLC, has no desire to spend additional funds until it’s known whether the proposed land changes can be approved.
The property owner is proposing to raise the property elevation to support additional development at the former golf course site, which it purchased in 2015 for $800,000, according to Olmsted County records.
Mark Schuleman, a Berkshire Road resident, living south of Cascade Creek said he and his neighbors are worried the proposed changes will affect their homes.
“We are next-door neighbors, and we have a concern of flooding,” he said, asking the commission to pause the request for added review.
The developer and city staff have been studying the proposal since an environmental assessment was approved at the start of 2025, but Schuleman raised concerns about changes made during that time.
He pointed out the assessment was based on plans to build up the site with an estimated 240,000 cubic yards of soil, while current plans point to using 72,000 cubic yards.
“We’re saying that at this point the record isn’t ready,” he told the commission.
Tointon said the discrepancy is based on moving from initial plans to fill the entire site to a flood protection model, raising it to 2 feet above the 100-year flood level. The current plan calls for only raising proposed building sites to the added height, leaving the rest of the site at the 100-year flood level.
With a large percentage of the site currently below the 100-year flood elevation, any development will require creating ponds along the south side of the property, which will provide fill used to raise the areas closer to Country Club Road.
Tointon said no soil is expected to be imported to the site to adjust elevations.
Mohler also pointed out any work, from grading to future construction, is required to ensure the changes don’t have negative impacts on neighboring properties.
Seth Loken, Rochester water resources engineer, said that’s been a primary focus of the staff review of the proposed site changes.
“This is pretty much an accounting exercise,” he said, pointing out plans must ensure the build up of one area is accompanied with the ability to capture water in another location on the same property.
Planning and Zoning Commission member Bob Cline, who cast the sole opposing vote to Wednesday’s recommendation, expressed some concern about the timing, noting future site plans could move forward before the site is prepared.
Tointon pointed to the potential for additional planning this year, but said the developer will be responsible for meeting the conditions of any approval, which will include creating a grading plan and addressing wetland requirements.
It’s not the first time ML Group has initiated efforts to develop the site. Earlier efforts have targeted the creation of apartment-style housing, townhouses and a senior living facility, and the City City council
approved a zoning change in 2015
to make such development possible.

Current site conditions are shown southeast of the intersection of Country Club Road and 45th Avenue Southwest in Rochester. A conditional-use permit is being requested to elevate parts of the 49-acre site to make way for potential development.
Contributed / City of Rochester
While the request for a conditional-use permit isn’t tied to a specific project, the application notes development of a multifamily rental project is being considered. The potential scale of the proposed apartment complex is not defined in the application, and developer representatives have said future plans will spur additional review.
Mohler said if the City Council approves the requested work at the site, the developer will still need to go through the city’s approval process for any development, which would spur added engagement with neighbors, as well as the potential for added review by the Planning and Zoning Commission, depending on what plans emerge.
For now, the next level of review will be at a future City Council meeting, which will include a public hearing to gather input on the proposed conditional-use permit.